News
16.11.2021 - O-I Manufacturing a.s. Nové Sedlo, Czech republic
General overhaul of the Furnace, design and delivery of partial steel structure
28.08.2021 - General overhaul of the furnace and foreheart, Knauf Insulation, France plant Lannemezan
On August 28, 2021, our already 2nd overhaul of the furnace and foreheart began at the Knauf Insulation Lannemezan plant, located at the foot of the Pyrenees. Our scope includes also design and installation of channel inderect cooling (fans, ducting and platform), furnace refractory demolition and installation of new refractory and steel construction.
The overhaul will take 38 days (from glass to glass). A time-lapse video is coming soon, stay tuned.
17.07.2021 - Our new mini-helper for lifting heavy loads
Lifting loads up to 2.5 t in hard-to-reach areas is not an obstacle for us, our mini-helper will also walk through the door.

09.06.2021 - Burners replacement and modification of the lining on the device Styren, Synthos Kralupy nad Vltavou
Our company operates not only in glassworks but also in chemical plants such as Synthos Kralupy nad Vltavou. On the device Styren we replace gas burners, modify the lining associated with the replacement of burners and install security system.
12.04.2021 - Blowing wool installation in Canal 2, Knauf Insulation Krupka
The principle of glass wool production is constantly evolving and, thanks to modern technologies, is moving forward. The Knauf Insulation plant in Krupka upgrades and installs Blowing wool technology on channel 2. W Our company is keen to perform extensive modification of channel 2 refractory design and electrical heating system, which included upgrade of PLC software, HMI software and WinCC (SCADA) and start-up of system.